The commercial commissioning of the LNG Terminal in Hamina will take place at the beginning of Gas Year 2022. The objective is to provide all terminal services to the market as of 1 October 2021.

Capacity available for Gas Year 2022 will be offered for reservation from 1 April 2021.

Terminal rules

Finnish Energy Authority has approved Hamina LNG Oy terminal rules with a decision dated in 30.10.2020. 
These commercial rules and tariffs apply to 01.04.2021 – 30.09.2022

Release 30.9.2020

The commercial commissioning of the LNG Terminal in Hamina is now planned to take place in early April 2021. The transmission system connection will be taken into use in August 2021.

The objective is to bring the key services of the Terminal to the market during the second quarter in 2021. The commercial capacity reservation period of the Terminal services is in November and December 2020.
The commissioning schedule of the EPC contractor will become more specific towards the end of this year.