Finnish Energy Authority has approved Hamina LNG Oy terminal rules with a decision dated in 30.10.2020. 
These commercial rules and tariffs apply to 01.04.2021 – 30.09.2022

Capacity booking process

Hamina LNG Terminal capacity booking process has started and it will run from 11th of November 2020 until 11th of December 2020.
Instructions for capacity booking procedure.

Release 30.9.2020

The commercial commissioning of the LNG Terminal in Hamina is now planned to take place in early April 2021. The transmission system connection will be taken into use in August 2021.

The objective is to bring the key services of the Terminal to the market during the second quarter in 2021. The commercial capacity reservation period of the Terminal services is in November and December 2020.
The commissioning schedule of the EPC contractor will become more specific towards the end of this year.